NESTLE PREPARED FOODS
DESIGN BUILD WASTEWATER
PRE-TREATMENT PLANT ADDITIONS - PHASE II

 
PROJECT LOCATION: Mt. Sterling, KY

PROJECT COST: $1,200,000

DATE COMPLETED: AUGUST 2006

OWNER: NESTLE PREPARED FOODS


ENGINEER: GRW

  • Expansion of the wastewater pre-treatment plant
  • Expansion included a Sequencing Batch Reactor
  • Increased the capacity of the treatment facilities to 405,000 gallons per day (0.4 MGD)
  • Improvements made to upgrade the performance of an existing Dissolved Air Flotation
  • Air Flotation Thickener by adding a surfactants improved Dissolved Air Flotation System
  • New facilities will be automatically controlled via a programmable control system
  • Maximized effective energy use while producing a treated effluent that complies with discharge limits.