KINGSPORT, TENNESSEE
Holston Army Ammunitions Plant Industrial Waste Retention
PROJECT LOCATION: KINGSPORT, TENNESSEE
PROJECT COST: $2,100,000
DATE COMPLETED: APRIL 2000
OWNER: CORPS OF ENGINEERS
ENGINEER: CORPS OF ENGINEERS
Constructed 1,500 CY one million gallon concrete flow equalization and spill tanks
Installed ancillary force mains, valves and pumps