City of Murfreesboro, TN Case Study

Stones River Water Treatment Plant
Job Details
  • Construction of an expansion to the existing Stones River Water Treatment Plant
  • Constructed a new pretreatment chemical storage building
  • Constructed a post‐treatment chemical storage building
  • Constructed a membrane filtration building
  • Constructed a high-service pump building and clear well
  • Modified existing buildings and renovated
  • Graded, paved and relocated existing utilities and installed new utilities to the site
Project Location: Murfreesboro, Tennessee 
Project Cost: $40,315,634.00 
Date Completed: August, 2011 
Owner: City of Murfreesboro, TN
Engineer: Smith Seckman & Reid, Inc.