Rathbun Regional Water Association Case Study

2007 Water System Improvements ‐ Contract ‘B2’ Water Treatment Plant
Job Details
  • New 6.0 mgd water treatment facility
  • Completion of project started by another contractor who was removed after 45% completion
  • Concrete clear well and in‐ground tanks
  • High service pump / electrical building
  • 2 each vertical turbine Pumps; 3000 gpm, 300 hp
  • Surge control system
  • 8 each Sand Media Multi-wash Central Gravity Filters
  • 2 each high-rate, pulsating sludge blanket clarifiers in new concrete basins; 2,292 gpm capacity
  • Rotary positive displacement blower; 1080 icfm
  • Chemical storage and feed equipment
Project Location: Centerville, IA
Project Cost: $8,135,152.00 
Date Completed: October, 2013 
Owner: Rathbun Regional Water Assoc.
Engineer: McClure Engineering 