Project: 2005 Wastewater
Pretreatment Improvements
Value: $475,000
Process: Constructed an onsite pretreatment process; built a new raw waste pump station, new blower building, interior and exterior piping and concrete work. Installing owner provided DAF units and process equipment and piping in the existing pretreatment building. All of this work was performed in a short period of time and while the owner was in production of processing poultry.
|
|