SOMERSET, KENTUCKY
Client: City of Somerset
Project: New Raw Water Intake for Water Treatment Plant
Value: $ 4.6 Million
Process: Drilled 20’ diameter shaft approximately 60’ into rock; built 40’ extension above ground to pump house; bored 48” diameter micro tunnel 350’ into lake; installed 36” diameter intake pipe and screen on an H pile support system under water. |
A word from the plant operator: “We’ve hired BCI for two projects. They’re great to work with; they know their job and they get it done. They’re very cooperative with change orders and proactive about finding things that need revision. The laborers are very high caliber as well.”
--Kenny Brinson, Plant Operator
|